Our Process

The money is saved before the first shovel.

Most builders hand you a free ballpark and a lump sum. We do the opposite. We charge for the planning, show you every number, and then guarantee the maximum. Here is how that works from first call to keys.

Six stages, first call to keys.

01

The conversation.

You fill out the questionnaire. Seth reads it and, if the project is a fit, calls to talk through scope, budget, land, and timing. No charge, no sales pitch.

02

Pre-construction. 40 to 60 hours over one to two months.

This is the phase other builders skip. We design the house with you in 2D and 3D, write a scope of work for every line item, get current pricing from every trade and vendor, and produce a complete budget and schedule. We charge $100 per hour for this work. The full amount is credited back from your deposit when you sign a construction agreement. If you choose another builder, the plans and the budget are yours to take with you.

03

Engineering and agreement. One to three weeks.

An architect or engineer reviews and stamps the drawings. If the budget came in above your number, we redesign until it fits. Then we sign a cost-plus agreement with a guaranteed maximum price and a payment schedule.

04

Permits and site. Four to ten weeks.

Permit, survey, and any soil or environmental work. Site clearing, excavation, utilities, foundation. Site work is the largest unknown in any build, which is why the budget carries a contingency you can see.

05

Build. Six to twelve months.

Framing, roof, exterior, mechanicals, insulation, drywall, finishes, landscaping. Each phase is done by a specialist in that trade, selected and supervised by Seth. You walk the site with him at every stage. Progress reports arrive from the field, with photos, as the work happens.

06

Walkthrough and keys. One to two weeks.

A punch list you write with us, every item closed, a full orientation of the house and its systems, then the keys.

Cost-plus, guaranteed maximum, open book.

Every line in the budget shows the actual cost of labor and materials, a contingency for the unknown, and our fee. That total becomes the guaranteed maximum. If the project comes in under, the savings are yours. If it runs over, we absorb the difference. You can see the budget, the invoices behind it, and the schedule at any time.

Our Process: Cost Plus Custom Home Builder

See a real estimate.

A sample cost-plus estimate for an addition and remodel, in the format every client receives. Scopes of work for every line, quantities, rates, contingency, and fee, nothing hidden.

Plan a year or two ahead.

We keep a quarterly schedule and take on a small number of projects at a time. Most builds begin three months to a year after the agreement is signed. The best projects are the ones where the owners started talking to us before they bought the land.

Financing a custom build.

Construction financing is a two-step process. A construction loan covers land and the build, then converts or refinances into a permanent mortgage when the house is complete. Most lenders want strong credit and 20 percent down, though land equity can count toward it. Lenders who specialize in construction-to-permanent loans make this far simpler than a general bank.

“Seth was very clear in his estimate. His work was done with precision, utmost quality and attention to detail.”

S. Samuel

Start with the questionnaire.

Fourteen questions. Seth reads every one personally and calls within two business days if the project is a fit.